Extension Agreement:
When the Customer desires a Water Main to be extended to furnish Water Service to any property for residential, commercial or industrial use, the Customer (applicant) shall make a formal application and deposit with KCBPU an amount equal to the estimated cost of such connection, improvements or extension of the water distribution system, and shall sign and execute an agreement in a form satisfactory to KCBPU. If all work set forth in this agreement has not been completed within a two (2) year period, KCBPU may terminate the agreement or require an amendment including any increase in the initial deposit to offset any increase in construction cost.
KCBPU has two types of Main extension agreements:
Plan A is for extensions made interior to the development. Water Main extension costs are not refundable.
Plan B is for extensions exterior to the development. The initial cost of the extension shall be borne by the applicant. However, acreage charges shall be collected by KCBPU from other property owners within the Benefit Area as Water Service is provided. The acreage charges are refunded to the Customer who paid for the original extension. The acreage charge collected from other property owners will be proportional to the property area compared to the benefit area. Acreage charges shall not apply if KCBPU has an existing Water Main adjacent to the property. Acreage charges and Customer refunds are discontinued after 10 (ten) years, or 20 (twenty) years if installed prior to October 24, 2019.
Specifications:
The applicant shall pay an Engineering Design Services Fee as determined by KCBPU. KCBPU’s Civil Engineering Department will prepare the Water Main design and estimated costs for all new developments. A KCBPU selected contractor will provide the Water Main installation.
The applicant shall submit a plat plan that has been approved by the Unified Government along with plan and profile drawings 90 days prior to the desired date for commencement of Water Main construction in the proposed development, showing streets, sanitary sewers, subsurface (rock) data or rock borings, sidewalks and the number and type of proposed Structures. All data shall be submitted digitally on CD or with KCBPU permission uploaded to KCBPU’s FTP site in AutoCAD .dwg format. In an effort to respond in a timely manner to Main extension requests, digital drawings will not include X-ref’s or Z-coordinates. The original design and estimated costs for Water Main extensions will be based on the plans submitted and any revision of those plans. Revisions that materially affect the original design and estimated costs may require an addendum to the original agreement or execution or a new agreement.
The length of the requested extension shall be that distance from the nearest existing distribution Main of adequate capacity to the farthest point on the property being served or the last lot being served, as measured along the center line of existing and proposed street rights-of-way, unless a lesser distance shall be determined adequate by KCBPU.
The diameter and material of the Main to be installed shall be determined by KCBPU, based upon a consideration of the following factors:
- Provisions of adequate service to prospective Customers.
- Possible and contemplated future extensions of the Main to be installed.
- Fire protection needs existing or anticipated in the area to be served.
If KCBPU desires to make the extension with pipe of a larger diameter than that is reasonable required to serve the area to which the main is being extended, the additional cost for the larger diameter Main shall be borne by KCBPU.
Estimated Cost:
The total estimated cost of the proposed Water Main extension will be prepared by KCBPU and the applicant shall receive one copy. The estimate shall include the cost of easements, pipe, fittings, valves, fire hydrants, rock excavation, miscellaneous material, labor, supervision, inspection, engineering, insurance, accounting, taxes, permits, construction equipment and tools, restoration of right-of-ways and overhead expenses. If the applicant fails to submit subsurface (rock) data or rock borings, the cost estimate will be prepared using ten percent (10%) solid rock, fifteen percent (15%) machine rock and seventy-five percent (75%) common soil excavation.
Upon completion of the Water Main extension, all costs will be determined. If the actual cost is less than the estimated cost, a refund of the difference shall be made to the applicant. If the actual cost is greater than the estimated cost, the applicant shall make an additional payment to KCBPU.
Construction:
After execution of the Agreement, KCBPU will attempt to construct the Water Main extension at a time more desirable to the applicant; however, KCBPU should be allowed a minimum of twelve (12) weeks from date of application to schedule its contractor for this work.
KCBPU’s Contractor shall furnish all labor, equipment, tools and material necessary for the extension of the Water Main. All equipment, materials, construction methods and tools shall comply with applicable code of local, state and federal authorities.
All work in constructing the extension shall be subject to inspection and approval by KCBPU to ensure that such construction is in strict compliance with the construction specifications, drawings and plans.
Maintenance of the Water Main extension and appurtenances, street crossings and surface areas is KCBPU’s responsibility.
Special Conditions:
Whenever Water Main extensions are installed in other than dedicated public right-of-way, the applicant shall execute and convey, without cost to KCBPU, all easements necessary to construct and maintain the Water Main extension specified herein, prior to the installation of the Water Main.
The applicant shall provide line and grade stakes and complete grading along the alignment of the Main to within one-foot (1’) of the final grade prior to the installation of the Water Main.
Interest on Deposits:
KCBPU will pay no interest on the applicant’s deposit or on any refunded balances.
Title of Extension:
The full title, ownership and right of exclusive possession to all Water Mains installed under these rules shall be and remain the property of KCBPU, unless otherwise specifically stated.
Right to Further Extend:
KCBPU reserves the right to further extend the Water Mains from and beyond each Water Main extension made under these rules.
Execution of Agreements:
Only the General Manager shall have the authority to approve and execute Water Main Extension Petitions and Agreements on behalf of KCBPU. The General Manager has the right to negotiate with the applicant the terms and conditions for executed petitions and agreements; provided, that such developments contain at least 250 homes to be built in a single subdivision over a three (3) year period.